TechFlow reports that on November 17, according to Chaoxiang Research, Morgan Stanley released its Greater China semiconductor report on November 15, downgrading a number of ratings for cloud-side semiconductors and legacy memory, while maintaining overweight recommendations for CXMT and Nanya Technology.
The research report stated that the US team shifted approximately 5GW of new data center capacity from 2028 to 2029, equivalent to 20% of the originally projected new installations for 2028. Capital expenditure forecasts for hyperscalers in 2027 and 2028 remained unchanged at $1.6 trillion and $1.8 trillion, respectively.
The research report noted that the breadth of earnings upgrades is peaking, visibility into 2028 server production is weakening, and the shortage of legacy memory is narrowing; therefore, it chose to trim positions ahead of visible deceleration in cloud capex. Catalysts cited include weakening order momentum and moderating price hikes.